Last updated: February 25. 2014 11:39AM - 1408 Views
By - kkissiah@civitasmedia.com - 843-537-5261



Karen Kissiah | Cheraw ChronicleThe removal of this barge, which has been stationed in Teals Mill Pond for a couple of months, will cause the bridge and a portion of the road to be closed Wednesday, Feb. 26, from 8 a.m. until 4:30 p.m. The barge has hosted technicians conducting geological studies necessary for planning the construction of the permanent bridge. The new bridge, not expected to be completed for a couple of years, will stretch across the center of the pond and eliminate the sharp curve that currently exists.
Karen Kissiah | Cheraw ChronicleThe removal of this barge, which has been stationed in Teals Mill Pond for a couple of months, will cause the bridge and a portion of the road to be closed Wednesday, Feb. 26, from 8 a.m. until 4:30 p.m. The barge has hosted technicians conducting geological studies necessary for planning the construction of the permanent bridge. The new bridge, not expected to be completed for a couple of years, will stretch across the center of the pond and eliminate the sharp curve that currently exists.
Story Tools:

Font Size:

Social Media:

The Teals Mill Bridge, and a portion of the Teals Mill Road, will be closed Wednesday, Feb. 26, from approximately 8 a.m. until 4:30 p.m.


The South Carolina Department of Transportation issued a statement Tuesday saying the bridge “will be closed to allow a contractor to remove barges from the water.”


A detour will be in place utilizing Songbird road, James Teal Road and Hunts Mill Road.


The barges have been hosting technicians conducting studies for the construction of the permanent bridge, scheduled to completed in a couple of years. The new bridge will stretch across the center of the pond and eliminate the sharp curve over the spillway.